Why relative, not hours
People are poor at estimating absolute time but fairly good at comparing: "this is about twice as big as that". Points capture that comparison and stay stable as a team gets faster, whereas hour estimates drift.
How to start
- Pick a small, well-understood item the whole team knows and call it 2 or 3 points.
- Estimate other items relative to it.
- Use a coarse scale, often a modified Fibonacci sequence: 1, 2, 3, 5, 8, 13. The gaps widen because uncertainty grows with size.
- Anything above the top of your normal range should be split, not estimated.
Planning poker
- The Product Owner explains the item and answers questions.
- Each developer picks a card privately.
- Everyone reveals at once, which stops anchoring on the first voice.
- The highest and lowest explain their reasoning.
- Re-vote once or twice; then take the consensus or the larger number and move on.
The real value
The discussion after a 2 and a 13 are revealed together is worth more than the number. It surfaces a hidden assumption, a forgotten migration or a simpler approach.
Mistakes to avoid
- Comparing points between teams. Each team’s scale is its own.
- Converting points back into hours or days.
- Rewarding people or teams for more points. Inflation follows immediately.
- Spending more time estimating than the precision is worth.
Alternatives
Some teams drop estimates and split all items to roughly the same size, then count items. Others use T-shirt sizes for long-range planning. Pick what helps the team plan; the method matters less than the conversation.
Sources and further reading
- Schwaber, K. and Sutherland, J. (2020). The Scrum Guide. scrumguides.org.
- IICTP. TPBOK, Engineering Governance & Agile Delivery. iictp.org/standards/tpbok.
Go deeper: ADP™ credential · the TPBOK™ standard · Check your experience
IICTP is an independent technical credentialing body.