In this post
The idea in one sentence
The critical path is the longest chain of dependent tasks from start to finish; its length is the shortest possible duration of the project.
How to find it
- List the tasks and estimate each one’s duration.
- Record dependencies: which task must finish before another can start.
- Forward pass: working from the start, each task’s earliest start is the latest earliest-finish of the tasks it depends on.
- Backward pass: working from the end, each task’s latest finish is the earliest latest-start of the tasks that depend on it.
- Float (or slack) is latest start minus earliest start. Tasks with zero float form the critical path.
A worked example
- A. Design API: 3 days, no dependency.
- B. Build backend: 5 days, after A.
- C. Build frontend: 4 days, after A.
- D. Integration testing: 2 days, after B and C.
- Path A-B-D takes 10 days; path A-C-D takes 9. The critical path is A-B-D, so the project needs at least 10 days. C has 1 day of float: it can slip a day without moving the end date. B cannot slip at all.
What to do with it
- Put your strongest people and closest attention on critical tasks.
- To finish sooner, shorten the critical path: split a task, run work in parallel, or remove a dependency. Speeding up a task with float changes nothing.
- Re-check after every change. When a non-critical task slips past its float, the critical path moves.
Software-specific traps
- Hidden dependencies: a shared test environment, a security review, another team’s API. Write them down as tasks.
- Estimates are guesses. Add a buffer at the end of the critical path rather than padding every task.
- Integration is often the real critical task. Integrate early so it is not one big step at the end.
Sources and further reading
- IICTP. TPBOK, Engineering Governance & Agile Delivery. iictp.org/standards/tpbok.