Risk vs issue
A risk has not happened yet: it might. An issue is happening now. When a risk occurs, close it in the register and open an issue. Keeping the two apart stops the register from turning into a bug list.
What each entry needs
- Risk statement: "Because of [cause], [event] may happen, which would lead to [effect]."
- Likelihood and impact: a simple 1–5 scale for each. Multiply them to rank.
- Owner: one named person, not a team.
- Response: what you will do about it, and by when.
- Trigger: the early sign that it is starting to happen.
Four ways to respond
- Avoid: change the plan so the risk cannot occur, for example dropping an untested dependency.
- Reduce: make it less likely or less harmful, for example a spike, a prototype or a feature flag.
- Transfer: move the impact elsewhere, for example a vendor support contract or insurance.
- Accept: decide consciously to live with it, and record a fallback if it happens.
Technical risks people forget
- A single person who understands a critical system.
- Third-party APIs, licences or pricing that can change.
- Data migration and rollback.
- Security and compliance review late in the project.
- Performance at production scale, not test scale. See design for the failure you will have.
Keep it alive
Review the top five risks in an existing meeting every week or two rather than holding a separate risk meeting. Remove risks that have passed. A register that is only updated for audits is decoration.
Sources and further reading
- IICTP. TPBOK, Engineering Governance & Agile Delivery. iictp.org/standards/tpbok.
- IICTP. TPBOK, Infrastructure & Security. iictp.org/standards/tpbok.
Go deeper: ADP™ credential · the TPBOK™ standard · Check your experience
IICTP is an independent technical credentialing body.