In this post
Before the meeting
- The Product Owner brings an ordered backlog with the top items refined: clear, small and with acceptance criteria.
- The team knows its capacity: holidays, on-call, other commitments.
- Last Sprint’s unfinished work has been looked at, not silently carried over.
A simple agenda
- Why (Sprint Goal): the Product Owner proposes how the Sprint could increase value; the whole team agrees a goal.
- What: the Developers select items from the backlog that serve the goal and fit their capacity.
- How: the Developers break items into work for the first days, often tasks of a day or less.
- Check: does everyone believe the plan? If not, adjust scope now, not on day eight.
Good and weak Sprint Goals
- Weak: "Complete tickets 101 to 115." It is a list, not a goal.
- Better: "Customers can pay by bank transfer in the test environment."
- Better: "Cut search response time so the slowest pages load in under one second."
- A good goal lets the team drop or swap items and still succeed.
Common mistakes
- Planning to 100% of capacity, leaving no room for the unexpected.
- Bringing unrefined items and refining them in planning.
- The Product Owner or a manager assigning tasks to people.
- No Sprint Goal, so the Sprint becomes a to-do list.
- Forgetting non-feature work: technical debt, upgrades and on-call.
Estimating capacity
Teams often use past throughput or story points to sense-check how much fits. Treat these as a guide for the team, not a target. See velocity and burndown charts.
Sources and further reading
- Schwaber, K. and Sutherland, J. (2020). The Scrum Guide. scrumguides.org.
- IICTP. TPBOK, Engineering Governance & Agile Delivery. iictp.org/standards/tpbok.